What is NFPA 101?
NFPA 101, the Life Safety Code, is published by the National Fire Protection Association. It sets the construction, protection and occupancy features needed to protect people from fire, smoke and toxic gases. Unlike most building codes, it applies to existing buildings as well as new ones.
Many states and cities adopt it, often alongside the IBC and IFC. The Centers for Medicare and Medicaid Services (CMS) enforce the 2012 edition in health care facilities that take part in Medicare and Medicaid. The code is organised by occupancy (assembly, educational, health care, residential, business and so on), and the occupancy chapters set most of the detailed rules.
Does NFPA 101 require an evacuation plan?
NFPA 101 requires a written emergency plan in many occupancies. Recent editions list them in Section 4.8, including health care, ambulatory health care, residential board and care, assembly, educational, day care, hotels and dormitories, detention and correctional, and high-rise buildings. The emergency plan covers procedures such as raising the alarm, evacuation or relocation, and staff duties.
It also has one specific rule about posted diagrams: in hotels and dormitories, a floor diagram showing the actual floor layout, the exits and the room's location must be posted on or next to every guest room door (and in every dormitory resident room).
Other rules for posted evacuation maps come from the fire code (for example IFC Section 404, which lists what an evacuation plan should show), OSHA 29 CFR 1910.38 for workplaces, and local rules. Your AHJ decides what applies to your building.
What are the means of egress basics?
Chapter 7 sets the baseline egress rules for all occupancies. A means of egress has three parts: the exit access, the exit and the exit discharge. Most floors need at least two means of egress, three where the occupant load is more than 500 and four where it is more than 1,000. Doors serving 50 or more people must swing in the direction of travel. Travel distance, common path and dead-end limits are set in the occupancy chapters and depend on sprinklers. Exits must be marked where the way out is not readily apparent, and the means of egress must be lit, with emergency lighting where required.
Our NFPA 101 Chapter 7 guide goes through these section by section.
What should a posted evacuation plan show?
Whatever the rule that applies to your building, a good posted plan shows:
• "You are here", positioned for the spot where the plan hangs and turned the same way as the reader.
• The primary route to the nearest exit and a second route where there is one.
• Exits, exit stairs and, where present, areas of refuge and accessible exits.
• Fire extinguishers and manual fire alarm stations.
• The assembly point outside.
• Short instructions for what to do in a fire, and the emergency number.
• A map key and the date of the plan.
These are the same elements that ISO 23601 sets out for escape plans and that IFC Section 404 lists for evacuation plans.
What is different in health care buildings?
Hospitals and nursing homes (Chapters 18 and 19) cannot rely on everyone walking out. They use "defend in place": the building is divided into smoke compartments by smoke barriers, and staff move patients horizontally into the next compartment while the fire is contained. Fire drills are held at least quarterly on each shift. Many hospitals train staff on the RACE steps (rescue, alarm, contain, extinguish or evacuate).
Posted plans in these buildings should show the smoke compartment boundaries and the horizontal route to the next compartment, as well as the exits.
How do you keep plans current?
NFPA 101 requires the means of egress to be kept clear and usable at all times, and fire protection systems to be maintained. Plans go out of date when walls move, doors are locked or equipment is relocated. Good practice:
• Review every posted plan at least once a year and after any building work.
• Check the plans before each fire drill, and update them for anything the drill shows.
• Put the issue date on every plan, and replace every copy when you update it.
The AHJ or inspector may compare the posted plans with the building, so they should match.